Project name |
Double Transforming Station ÏÑ 110/35/10 kilowatt 2x25000 kilowatt “Ust-Labinsk Severnaya” |
Location of the project |
Ust- Labinskiy district |
Industry classification |
Fuel and energy complex |
Basic information about the project |
Project essence |
Within the framework of realization of the project construction of the Double Transforming Station ÏÑ 110/35/10 kilowatt 2x25000 kilowatt is planned |
Project capacity |
402960 megawatt/hour |
Financial estimation of the project |
Total cost of the project, mln rubles |
800 mln. Rub |
Investment capacity, mln rubles |
800 mln. Rub |
Conditions of investor participation |
Direct investments |
Payback period |
9.9 years |
Land characteristics |
Location |
Krasnodar region, Ust-Labinsk district, ul. Kommunalnaya (area of the water supply point) |
Land plot area (m2) |
10 000 (sq.ì.) |
Ground categories |
Area of settlements2x25ÌÂÀ |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
2x25ÌÂÀ |
1000 |
Gas supply |
- |
Not required |
Water supply |
50 cubic meters/year;d200mm |
200 |
Sewerage system |
d300 mm |
100 |
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
t. Ust-Labinsk |
3 |
Center of federal subject |
Krasnodar city |
65 |
Highway (regional, federal significance) |
Temryuk-Krasnodar-Kropotkin |
1 |
Roads of local significance |
Volnaya Str. |
1 |
Nearest railway station |
Ust-Labinskaya |
1,6 |
Nearest railway lines |
t. Ust-Labinsk |
1,6 |
Airport |
c. Krasnodar |
50 |
Seaport |
c. Novorossiysk |
230 |