Project name |
Construction of production areas for wood processing |
Location of the project |
Armavir Ñity |
Industry classification |
Industry |
Basic information about the project |
Project essence |
Creation of a production enterprise on wood processing on the territory of municipal formation town Armavir assumes construction of non residential areas having shops for sawing, protective wood processing and its storage. It is expected that this project will satisfy demands on qualitative servicing on wood processing area and positioned itself as a production enterprise. It is planned to use modern technologies |
Project capacity |
It is assumed to build non residential areas for sawing, protective wood processing and its storage. |
Financial estimation of the project |
Total cost of the project, mln rubles |
3 mln.rubles |
Investment capacity, mln rubles |
3 mln.rubles |
Conditions of investor participation |
Direct investments |
Payback period |
3,7 years |
Land characteristics |
Location |
Armavir, Northern industrial zone |
Land plot area (m2) |
5 000 m2 |
Ground categories |
Land of settlements |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
PS-(35/6)110/10kwatt |
275 |
Gas supply |
D=377 |
250 |
Water supply |
D=250 |
50 |
Sewerage system |
D=600 |
130 |
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
The Central part of Armavir |
3,8 |
Center of federal subject |
Krasnodar |
250 |
Highway (regional, federal significance) |
FAD «Caucasus» |
7,5 |
Roads of local significance |
«Armavir – Otradnaya» |
2,0 |
Nearest railway station |
Railway station «Armavir-1», Railway station «Àrmavir-2» |
3,8 , 2,3 |
Nearest railway lines |
|
0.2 |
Airport |
The airport of Krasnodar |
200 |
Seaport |
Novorossijsk |
360 km |