Project name |
Construction of the workshop for manufacture cabinet furniture |
Location of the project |
Beloglinskiy district |
Industry classification |
Industry |
Basic information about the project |
Project essence |
Shop creation on manufacture of case furniture, adjustment of a dealer network on deliveries of given production in large trading networks of Krasnodar territory, the Rostov region and Stavropol Territory. Replacement of production of foreign manufacturers - domestic |
Project capacity |
Planned volumes of realization: a table the worker - 60 pieces / month, a case - 44 pieces / month, a bedside table - 60 pieces / month, a rack - 20 pieces / month |
Financial estimation of the project |
Total cost of the project, mln rubles |
4,211 |
Investment capacity, mln rubles |
4,211 |
Conditions of investor participation |
Direct investments |
Payback period |
2 years |
Land characteristics |
Location |
Ratimova Street, Uspenskaya village, Beloglinskiy district, Krasnodar region |
Land plot area (m2) |
1100 |
Ground categories |
Settlement lands |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
10 kV |
600 |
Gas supply |
GDS |
550 |
Water supply |
D=100 mm |
800 |
Sewerage system |
It is absent |
- |
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
Belaya Glina village |
42 |
Center of federal subject |
Krasnodar city |
280 |
Highway (regional, federal significance) |
Tikhoretsk - Salsk |
42 |
Roads of local significance |
rural road |
0,6 |
Nearest railway station |
Beloglinskaya |
46 |
Nearest railway lines |
Single lane |
46 |
Airport |
Krasnodar city |
280 |
Seaport |
Novorossiisk city |
425 |