Construction plant of zinc metal

Project name Construction plant of zinc metal
Location of the project Korenovskiy district
Industry classification Industry
Basic information about the project
Project essence Construction of hot galvanized steel in Korenovsky district
Project capacity Up to 9 tons of metal a day
Financial estimation of the project
Total cost of the project, mln rubles 60,2 mln. rbl
Investment capacity, mln rubles 60,2 mln. rbl
Conditions of investor participation Direct investments
Payback period 4,2 years
Land characteristics
Location Korenovsky district, Korenovsk city, (turning to the AP, South)
Land plot area (m2) 100000 m2
Ground categories Earth settlements
Characteristics of existing engineering infrastructure
Infrastructure typeCapacity, diameterDistance to the connection point (m)
Power supply from the projected SS 110/35/10 kV "Korenovkaya Industrial Zone" 5000
Gas supply from the existing steel underground high pressure gas pipeline D-114 mm, leading to the village South 400
Water supply construction of water intake capacity of 30 m3 / day 10
Sewerage system construction of small sewage treatment plants On the territory
Distance up to the large residential places and objects of transport infrastructure
Remoteness fromNameDistance (km)
Municipality center Korenovsk city 5
Center of federal subject Krasnodar city 67
Highway (regional, federal significance) M4 Don 7
Roads of local significance Mayakovskogo street 1
Nearest railway station Station Korenovsk 3
Nearest railway lines 2,5
Airport Airport Krasnodar 77
Seaport Novorossiysk 266