Project name |
Construction plant of zinc metal |
Location of the project |
Korenovskiy district |
Industry classification |
Industry |
Basic information about the project |
Project essence |
Construction of hot galvanized steel in Korenovsky district |
Project capacity |
Up to 9 tons of metal a day |
Financial estimation of the project |
Total cost of the project, mln rubles |
60,2 mln. rbl |
Investment capacity, mln rubles |
60,2 mln. rbl |
Conditions of investor participation |
Direct investments |
Payback period |
4,2 years |
Land characteristics |
Location |
Korenovsky district, Korenovsk city, (turning to the AP, South) |
Land plot area (m2) |
100000 m2 |
Ground categories |
Earth settlements |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
from the projected SS 110/35/10 kV "Korenovkaya Industrial Zone" |
5000 |
Gas supply |
from the existing steel underground high pressure gas pipeline D-114 mm, leading to the village South |
400 |
Water supply |
construction of water intake capacity of 30 m3 / day |
10 |
Sewerage system |
construction of small sewage treatment plants |
On the territory |
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
Korenovsk city |
5 |
Center of federal subject |
Krasnodar city |
67 |
Highway (regional, federal significance) |
M4 Don |
7 |
Roads of local significance |
Mayakovskogo street |
1 |
Nearest railway station |
Station Korenovsk |
3 |
Nearest railway lines |
|
2,5 |
Airport |
Airport Krasnodar |
77 |
Seaport |
Novorossiysk |
266 |