Building an enterprise producing glass, windows, doors, and mirror in Novodmitryevskaya settlement

Project name Building an enterprise producing glass, windows, doors, and mirror in Novodmitryevskaya settlement
Location of the project Severskiy district
Industry classification Industry
Basic information about the project
Project essence Building of new capacities in the Novodmitrievsky settlement. Assortment planned to launch - windows, doors, stained-glass windows and other metalloplasticrotecting building designs of PVC, and as products from glass, mirrors and double-glazed windows.
Project capacity The planned volume of sells of finished goods-14300 m sq. in a year for a total sum of 45 370 million rubles in a year.
Financial estimation of the project
Total cost of the project, mln rubles 29,05 mln.rbl
Investment capacity, mln rubles 29,05 mln.rbl
Conditions of investor participation Direct investments
Payback period 3,6 years
Land characteristics
Location Krasnaya st, Novodmitriyevskiy settlement of Severskiy district
Land plot area (m2) 10 000
Ground categories The grounds of settlement
Characteristics of existing engineering infrastructure
Infrastructure typeCapacity, diameterDistance to the connection point (m)
Power supply from installation PS 35\6 kw «Novodmitrievskaya» power 2245,2 kWt 0
Gas supply from nearest gas line ,d of pipe line 220 mm, meddle power pressure 0,25 êÏà 350
Water supply Power – 5200 kub.m. 100
Sewerage system There is not central water drain of sewage station To build local water drain of sewage station
Distance up to the large residential places and objects of transport infrastructure
Remoteness fromNameDistance (km)
Municipality center Severskaya town 23
Center of federal subject Krasnodar city 14
Highway (regional, federal significance) Federal auto road Êrasnodar-Novorossiysk 0,4
Roads of local significance 0,025
Nearest railway station Afipskaya station 3,4
Nearest railway lines 0,5
Airport 22
Seaport 132