Plant on goffer package production

Project name Plant on goffer package production
Location of the project Tbilisskiy district
Industry classification Industry
Basic information about the project
Project essence Organization of knobby packing and gofferboxes production
Project capacity 150 mln. m? a year
Financial estimation of the project
Total cost of the project, mln rubles 29,9 mln. rub.
Investment capacity, mln rubles 29,9 mln. rub.
Conditions of investor participation Direct investments
Payback period 4.1 year
Land characteristics
Location Tbilisskaya village, 80 “B” Proletarskaya street
Land plot area (m2) 10000 sq.m
Ground categories Settlements land
Characteristics of existing engineering infrastructure
Infrastructure typeCapacity, diameterDistance to the connection point (m)
Power supply from existing power station 110/35/10 kw 1000
Gas supply no necessary -
Water supply from existing water pipe d-100mm., free pressure in net 1,5 atm. 2250
Sewerage system local -
Distance up to the large residential places and objects of transport infrastructure
Remoteness fromNameDistance (km)
Municipality center Tbilisskaya village
Center of federal subject Krasnodar city 104
Highway (regional, federal significance) Temryuk-Krasnodar-Kropotkin 2,0
Roads of local significance existing motorway with asphaltic concrete pavement 0,17
Nearest railway station station of Grechishkino 3,7
Nearest railway lines Krasnodar-Kropotkin 0,8
Airport airport of Krasnodar 94
Seaport port of Novorossiysk 280