Project name |
Greenhouse complex |
Location of the project |
Tbilisskiy district |
Industry classification |
Agriculture |
Basic information about the project |
Project essence |
It is supposed to use hydroponics method of vegetable growing, the essence of which is periodical giving of nutrient solution to the plant roots |
Project capacity |
10 hectare |
Financial estimation of the project |
Total cost of the project, mln rubles |
28,3 mln. rbl |
Investment capacity, mln rubles |
28,3 mln. rbl |
Conditions of investor participation |
Direct investments |
Payback period |
4,87 year |
Land characteristics |
Location |
East part of Geymanovskaya village in Tbilisskaya district |
Land plot area (m2) |
100000 sq.m. |
Ground categories |
Settlements land |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
from existing power station 35/10 kw |
500 |
Gas supply |
no necessary |
- |
Water supply |
from existing water pipe d-100mm., free pressure in net 1,5 atm. |
400 |
Sewerage system |
local |
- |
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
Tbilisskaya village |
10,5 |
Center of federal subject |
Krasnodar city |
110 |
Highway (regional, federal significance) |
Temryuk-Krasnodar-Kropotkin |
15,6 |
Roads of local significance |
existing motorway with asphaltic concrete pavement |
0,05 |
Nearest railway station |
station of Grechishkino |
12,6 |
Nearest railway lines |
Krasnodar-Kropotkin |
12,6 |
Airport |
airport of Krasnodar |
100 |
Seaport |
port of Novorossiysk |
290 |