Construction of green house complex in Aleksee-Tenginskaya village

Project name Construction of green house complex in Aleksee-Tenginskaya village
Location of the project Tbilisskiy district
Industry classification Agriculture
Basic information about the project
Project essence It is supposed to use hydroponics method of vegetable growing, the essence of which is periodical giving of nutrient solution to the plant roots
Project capacity 440 ton a year
Financial estimation of the project
Total cost of the project, mln rubles 29,99 mln. rbl.
Investment capacity, mln rubles 29,99 mln. rbl.
Conditions of investor participation Direct investments
Payback period 4,1 year
Land characteristics
Location 0,7 km to the east from Aleksee-Tenginskaya village of Tbilisskaya district
Land plot area (m2) 152815 sq.m.
Ground categories Settlements land
Characteristics of existing engineering infrastructure
Infrastructure typeCapacity, diameterDistance to the connection point (m)
Power supply from existing power station 35/10 kw 500
Gas supply no necessary -
Water supply From own artesian well -
Sewerage system local -
Distance up to the large residential places and objects of transport infrastructure
Remoteness fromNameDistance (km)
Municipality center Tbilisskaya village 17
Center of federal subject Krasnodar city 118
Highway (regional, federal significance) Temryuk-Krasnodar-Kropotkin 19
Roads of local significance existing road with gravel surfacing comes to the plot 2,4
Nearest railway station station of Grechishkino 18,5
Nearest railway lines Krasnodar-Kropotkin 18,5
Airport airport of Krasnodar 108
Seaport port of Novorossiysk 302