Project name |
Construction of the workshop for manufacture of frozen half-finished products |
Location of the project |
Beloglinskiy district |
Industry classification |
Agriculture |
Basic information about the project |
Project essence |
Within the project realization manufacture and a frost of half-finished products of cutlets, a stuffed cabbage, fritters with a various stuffing, and as vegetables and fruit is planned |
Project capacity |
The project provides manufacturing: - The frozen meat half-finished products, volume of realization of 4014 tons in a month; - The frozen fruit-and-vegetable half-finished products, volume of realization of 3838 tons in a month; - The frozen half-finished products from meat and the test, volume of realization of 4160 tons a month |
Financial estimation of the project |
Total cost of the project, mln rubles |
3,661 |
Investment capacity, mln rubles |
3,661 |
Conditions of investor participation |
Direct investments |
Payback period |
2 years |
Land characteristics |
Location |
Zapadniy village, Krasnodar region (bakery area) |
Land plot area (m2) |
1000 |
Ground categories |
Settlement lands |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
10 kV |
25 |
Gas supply |
GDS |
25 |
Water supply |
D=100 mm |
25 |
Sewerage system |
It is absent |
- |
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
Belaya Glina village |
30 |
Center of federal subject |
Krasnodar city |
270 |
Highway (regional, federal significance) |
Novopokrovskaya-Egorlik Rostov-Stavropol Tikhoretsk - Salsk |
0,15 23 33 |
Roads of local significance |
rural road |
0,01 |
Nearest railway station |
Beloglinskaya |
33 |
Nearest railway lines |
Single lane |
33 |
Airport |
Krasnodar city |
270 |
Seaport |
Novorossiisk city |
415 |