Project name |
Construction of an enterprise for quarrying of a sapropel and processing it to a humus in Zarechniy village in Novopokrovskiy district |
Location of the project |
Novopokrovskiy district |
Industry classification |
Agriculture |
Basic information about the project |
Project essence |
The project provides for the construction of an enterprise for quarrying of a sapropel and processing it to a humus in Zarechniy village in Novopokrovskiy district. |
Project capacity |
Production volume during the year: 8450 t. |
Financial estimation of the project |
Total cost of the project, mln rubles |
200 mil. rubles |
Investment capacity, mln rubles |
200 mil. rubles |
Conditions of investor participation |
Direct investments |
Payback period |
4,8 year |
Land characteristics |
Location |
Municipality Novopokrovskiy District, Pokrovskoe rural settlement, Zarechniy village, Shirokaya street w/n |
Land plot area (m2) |
150 000 |
Ground categories |
Lands of the settlements |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
|
250 |
Gas supply |
159 mm |
1350 |
Water supply |
|
300 |
Sewerage system |
|
airproof digestion tank |
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
Novopokrovskay |
10 km |
Center of federal subject |
City of Krasnodar |
195 km |
Highway (regional, federal significance) |
|
2 km |
Roads of local significance |
|
- |
Nearest railway station |
Station Ey |
15 km |
Nearest railway lines |
Station Ey |
15 km |
Airport |
City of Krasnodar |
196 km |
Seaport |
Novorossiysk |
386 km |