Construction of hothouse complex with use of geothermal water supply

Project name Construction of hothouse complex with use of geothermal water supply
Location of the project Otradnenskiy district
Industry classification Agriculture
Basic information about the project
Project essence It is supposed, that for construction of a hothouse complex in vil-lage Poputnaya Otradnensky of Krasnodar region with a total area nearby 36 000 m2, distributed proportionally the ground area is al-located for 4 zones on 9000 sq.m. under each kind of production. Following erected objects are included in structure of a hothouse complex: - Drilling hole (200m., Ò outside = + 40-50°C) and installment of heat exchanging contour; - Erection of the administrative module and a premise of laborato-ry; - Hothouses; - A platform for sorting and temporary storage of finished goods.
Project capacity 1. Cucumbers - 693 tons/years 2. Tomatoes - 144 tons/years 3. Salad - 315 tons/years 4. Pepper - 225,9 tons/years Volume of proceeds 60408,3 thousand roubles (without VAT)
Financial estimation of the project
Total cost of the project, mln rubles 55,0 mln. rub.
Investment capacity, mln rubles 55,0 mln. rub.
Conditions of investor participation Direct investment (100%)
Payback period 5,25 years
Land characteristics
Location Krasnodar region, Otradnensky district, village Poputnaya, street Sadovaya, ¹57
Land plot area (m2) 36 000 sq. m.
Ground categories Settlement lands
Characteristics of existing engineering infrastructure
Infrastructure typeCapacity, diameterDistance to the connection point (m)
Power supply ÊÒP 100KVA line-10kW Necessary to build ÊÒP and line -10kW 125 meters
Gas supply No need 1.Tower «Rozhnovsko-go» V=25m3, Dbringing water line = 57 mm, 2. Dmain water line = 150mm Dbringing water line = 25mm
Water supply 1. Technical water supply: construction of pump station on river Bey-Murza-Chekhrak is necessary. with submission on a tower «Rozhnovskogo», 2. For drinking water supply: installment of 150 meters of a water pipe is necessary Vseptic=7,2m2 Dpipe=100-150mm
Sewerage system 5-6 meters (from septic to buildings)
Distance up to the large residential places and objects of transport infrastructure
Remoteness fromNameDistance (km)
Municipality center village Otradnaya 10
Center of federal subject city Krasnodar 290
Highway (regional, federal significance) Rostov-on-Don – Makhachkala 70
Roads of local significance village Otradnaya – town Armavir 0,03
Nearest railway station town Armavir 70
Nearest railway lines town Armavir 70
Airport town Armavir 70
Seaport town Novorossiysk 420