Project name |
Agriculture "Adagum" |
Location of the project |
Krimskiy district |
Industry classification |
Agriculture |
Basic information about the project |
Project essence |
The project will include industrial zones with production function, processings and distributions of agricultural production, the logistical centres and auxiliary manufacture. The planned complex will render services in granting in rent of the industrial areas. All object will be executed in uniform architectural style. |
Project capacity |
It is annually planned to lease 219 269 sq.m. of floor spaces. |
Financial estimation of the project |
Total cost of the project, mln rubles |
6729,4 million rbl. |
Investment capacity, mln rubles |
6729,4 million rbl. |
Conditions of investor participation |
Direct investments |
Payback period |
10,1 years |
Land characteristics |
Location |
The Krymsk area, Adagumsky rural settlement, section 8, contour 4. |
Land plot area (m2) |
507 000 m2 |
Ground categories |
The earths of an agricultural purpose |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
Line from site PS110/35 kV Varenikovsky |
6500 |
Gas supply |
Dm-70 Till 2000 m3/hour |
4200 |
Water supply |
Du-100 mm, till 21 m3/hour |
No, drilling of chinks |
Sewerage system |
Building of independent treatment facilities |
No |
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
Krymsk |
37 |
Center of federal subject |
The city of Krasnodar |
147 |
Highway (regional, federal significance) |
Krymsk-Dzhiginka |
1 |
Roads of local significance |
Roads Poselkovye |
0 |
Nearest railway station |
The item Krymsk |
30 |
Nearest railway lines |
Krasnodar-Anapa |
1 |
Airport |
Anapa |
40 |
Seaport |
Novorossijsk |
60 |