The company producing drinking water

Project name The company producing drinking water
Location of the project Abinskiy district
Industry classification Agriculture
Basic information about the project
Project essence The project involves the establishment of the enterprise, which will receive water from wells and to market the products obtained primarily by the large bulk
Project capacity 1 500 000 million bottles a year of conditional
Financial estimation of the project
Total cost of the project, mln rubles 18
Investment capacity, mln rubles 18
Conditions of investor participation Direct investments, extra means
Payback period 1,9 years
Land characteristics
Location Settlement Ahtyrsky street Podselochnaja
Land plot area (m2) 3500
Ground categories land settlements
Characteristics of existing engineering infrastructure
Infrastructure typeCapacity, diameterDistance to the connection point (m)
Power supply from passing near the site of power lines 500
Gas supply Urban Pipeline 500
Water supply artesian well installation of a water tower
Sewerage system no local treatment facilities construction septic tanks
Distance up to the large residential places and objects of transport infrastructure
Remoteness fromNameDistance (km)
Municipality center city Abinsk 8
Center of federal subject city Krasnodar 80
Highway (regional, federal significance) The highway Krasnodar - Novorossisk 3
Roads of local significance Arenít present Nearby
Nearest railway station Abinsky, linear 15, 5
Nearest railway lines Krasnodar-Novorossisk 5
Airport Krasnodar, Anapa 100, 100
Seaport Novorossisk, Temryuk 90, 115