Project name |
Mini grain elevator construction |
Location of the project |
Kurganinskiy district |
Industry classification |
Agriculture |
Basic information about the project |
Project essence |
Structure construction, technical equipment buying, carrying out a primary developed works, staff reception are required for grain elevator operation |
Project capacity |
Dispatch and storage of grain crops with the productive volume of 30 000 tones at ones |
Financial estimation of the project |
Total cost of the project, mln rubles |
103,922 mln.rub. |
Investment capacity, mln rubles |
103,922 mln.rub. |
Conditions of investor participation |
Direct investments |
Payback period |
2,9 years |
Land characteristics |
Location |
Krasnodar region, Kurganinsky district, Kurganinsk town, Mihailovskoe highway,21 |
Land plot area (m2) |
15 000 sq.m. |
Ground categories |
residential places ground |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
VL-10 kV |
50,0 |
Gas supply |
From the operating high pressure gas pipeline on the Mihailovskoe highway, steel pipe diameter 100 mm |
800,0 |
Water supply |
From the operating water supply system on the crossing of Shosseinaya street and Zavodskaya street steel pipe diameter 100 mm |
1600,0 |
Sewerage system |
In the operating sewerage system on the crossing Shosseinaya street and Zavodskaya street a/c pipe diameter 200 mm |
1600,0 |
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
Kurganinsk town |
0 |
Center of federal subject |
Krasnodar city |
168,6 |
Highway (regional, federal significance) |
Ust-Labinsk-Labinsk-Upornaya |
0,8 |
Roads of local significance |
Mihailovskoe highway |
0,8 |
Nearest railway station |
Kurgannaya station |
4,05 |
Nearest railway lines |
Kurganinsk-Shedok |
2,0 |
Airport |
Krasnodar city |
171,6 |
Seaport |
Tuapse city |
350 |