Construction of waste recycling plant

Project name Construction of waste recycling plant
Location of the project Starominskiy district
Industry classification Housing and communal services
Basic information about the project
Project essence Construction of waste recycling plant on the territory of municipal formation Starominsky district. The plant will consist of three complexes. The project helps decide waste recycling problem using ecologically secure technology, getting energy and products for further use
Project capacity 15000 tons
Financial estimation of the project
Total cost of the project, mln rubles 18
Investment capacity, mln rubles 18
Conditions of investor participation Direct investments
Payback period 3,2 yers
Land characteristics
Location District of scramble hard home departure, Starominskaya village, Krasnodar region
Land plot area (m2) 9500
Ground categories The Earth of settlements
Characteristics of existing engineering infrastructure
Infrastructure typeCapacity, diameterDistance to the connection point (m)
Power supply Electric mains a high-voltage line - 10 kV Passes on territory of the area
Gas supply No -
Water supply Main water pipe MB-1, steel diameter of 800 mm 200
Sewerage system Construction of locally clearing buildings -
Distance up to the large residential places and objects of transport infrastructure
Remoteness fromNameDistance (km)
Municipality center Starominskaya village
Center of federal subject Krasnodar city Rostov - on - Don city 180 120
Highway (regional, federal significance) Krasnodar - Yeisk Azov – Aleksandrovka –Starominskaya Starominskaya – Kuschevskaya Starominskaya – Leningradskaya – Pavlovskaya M4 «Don» 5 4 3 12 56
Nearest railway station Starominskaya railway station 1 railway station 2 railway station 8 10
Airport Krasnodar city Rostov - on - Don city 180 120
Seaport Yeisk city Azov city Novorossiysk city 60 80 360