Project name |
Redevelopment of city block No.169 |
Location of the project |
Krasnodar city |
Industry classification |
House building |
Basic information about the project |
Project essence |
Redevelopment of residential block No. 169 located in the central part of Krasnodar Construction of residential buildings of over ten storeys in height intended |
Project capacity |
48 360 m2 |
Financial estimation of the project |
Total cost of the project, mln rubles |
48,7 |
Investment capacity, mln rubles |
48,7 |
Conditions of investor participation |
Direct investments |
Payback period |
3,11 |
Land characteristics |
Location |
Krasnodar City, Central Ward, City Block No.169 bounded by Yankovskogo, Gorkogo, Levanevskogo and Chapaeva streets |
Land plot area (m2) |
20676,4 |
Ground categories |
Land of settlement |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
1400 kw |
connection to be made to the power dis-tribution network of the Substation “Yuzhnaya” |
Gas supply |
not planned |
not planned |
Water supply |
1,148.5 cmb/24 h |
connection to be made to the water distri-bution network in Chapaeva street, partic-ipation in modernizing the water distribu-tion network required |
Sewerage system |
1,148.5 m3/24 h |
connection to be made to the sewage net-work in Levanevskogo and Chapaeva streets |
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
|
Immediate city center |
Center of federal subject |
Krasnodar City |
– |
Highway (regional, federal significance) |
Krasnodar- Novorossiysk |
3 |
Roads of local significance |
Levanevskogo st. |
immediately adjacent |
Nearest railway station |
Krasnodar-1 |
3 |
Nearest railway lines |
|
3 |
Airport |
Krasnodar |
10-12 |
Seaport |
Novorossiysk |
150 |