Project name |
Placement the low rise cottage small town for 30 houses |
Location of the project |
Otradnenskiy district |
Industry classification |
House building |
Basic information about the project |
Project essence |
Construction of 30 cottages by a total area 3000 sq.m. (fast erected house construction) |
Project capacity |
Total area 3000 sq.m. (30 cottages on 100 m2) |
Financial estimation of the project |
Total cost of the project, mln rubles |
50,725 mln. rub. |
Investment capacity, mln rubles |
50,725 mln. rub. |
Conditions of investor participation |
Direct investment (100%) |
Payback period |
2,4 years |
Land characteristics |
Location |
Village Otradnaya, street 2-nd and 3-d Sadoviy lane (south side of the village) |
Land plot area (m2) |
30 000 sq. m. |
Ground categories |
Settlement lands |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
ÊÒP-160ÊÂÀ, line 0,4êÂ, line 10ê |
600, 100 |
Gas supply |
D=89 mm |
0 (from existing gas line) |
Water supply |
Vtank=4,0 m3 |
0 (In connection with absence of a water planting network and the necessary debit of water on a wa-ter-fence of village Otradnaya it is necessary to provide an independent source of wa-ter supply) |
Sewerage system |
Vseptic = 10,8 m3 Dpipe=100-150mm |
5-6 meters (from building) |
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
village Otradnaya |
0 |
Center of federal subject |
city Krasnodar |
300 |
Highway (regional, federal significance) |
Rostov-on-Don – Makhachkala |
80 |
Roads of local significance |
village Udobnaya – village Otradnaya(street Yuzhnaya) – town Armavir |
1,1 |
Nearest railway station |
town Armavir |
80 |
Nearest railway lines |
town Armavir |
80 |
Airport |
town Armavir |
80 |
Seaport |
town Novorossiysk |
440 |