Project name |
Houses building in stanitsa Vozdvizhenskaya |
Location of the project |
Kurganinskiy district |
Industry classification |
House building |
Basic information about the project |
Project essence |
Project includes the construction of 36 houses stanitsa Vozdvizhenskaya on the Stepnaya street. It is supposed to provide construction plot with engineering infrastructure and develop design estimates |
Project capacity |
putting into operation the 1184 sq.m. of houses |
Financial estimation of the project |
Total cost of the project, mln rubles |
41,738 mln.rub |
Investment capacity, mln rubles |
41,738 mln.rub |
Conditions of investor participation |
Direct investments |
Payback period |
1,8 years |
Land characteristics |
Location |
Kurganinsky district, stanitsa Vozdvizhenskaya, Stepnaya street |
Land plot area (m2) |
71580 sq.m. |
Ground categories |
residential places ground |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
VL-10 kilovolt |
20 ,0 |
Gas supply |
Operating gas pipeline |
1000,0 |
Water supply |
Cast iron, diameter 150 mm |
2500,0 |
Sewerage system |
- |
- |
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
Kurganinsk town |
50 |
Center of federal subject |
Krasnodar city |
117 |
Highway (regional, federal significance) |
Ust-Labinsk-Labinsk-Upornaya |
0,3 |
Roads of local significance |
Lenina street |
0,25 |
Nearest railway station |
Kurgannaya station |
54 |
Nearest railway lines |
Armavir-Tuapse |
55 |
Airport |
Krasnodar city |
125 |
Seaport |
Tuapse city |
295 |