Project name |
Plant for production of polymer-modified bitumen and bitumen-polymer emulsions |
Location of the project |
Pavlovskiy district |
Industry classification |
Production of construction materials |
Basic information about the project |
Project essence |
Polymer - Modified bitumen - is the product obtained in industrial conditions as a result of mixing of bitumen and polymers. Bituminous emulsion is used for waterproofing of buildings and structures for construction and repairing of soft roofs, as well as many road technology |
Project capacity |
Sell Bitumen 23600 tons in year. Sales polymer 16800 tons in year. |
Financial estimation of the project |
Total cost of the project, mln rubles |
200 mill. rbl |
Investment capacity, mln rubles |
200 mill. rbl |
Conditions of investor participation |
Direct investmentsr |
Payback period |
2 years |
Land characteristics |
Location |
Krasnodar region, Pavlovsky District, southern part of the village Pavlovsk |
Land plot area (m2) |
30 000 (m2) |
Ground categories |
The grounds of a settlements |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
Introduce of PS 110/35/10 kV "Western" |
4000 |
Gas supply |
Gas pressure d = 159 mm 6 atm. |
130 |
Water supply |
Need to build artesian well |
within the boundaries of the land |
Sewerage system |
Construction of local treatment facilities |
within the boundaries of the land |
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
The Pavlovskaya |
- |
Center of federal subject |
Krasnodar city |
120 |
Highway (regional, federal significance) |
federal roads "Don" |
6 |
Roads of local significance |
- |
0,350 |
Nearest railway station |
Railway station «Sosyka – Eisk», Railway station«Sosyka –Rostov» |
4,5, 6,0 |
Nearest railway lines |
- |
0,030 |
Airport |
The Krasnodar |
126 |
Seaport |
The Eisk |
162 |