Project name |
Brick plant |
Location of the project |
Tbilisskiy district |
Industry classification |
Production of construction materials |
Basic information about the project |
Project essence |
Brick plant construction in north-east part of Tbilisskaya village. Production of full single brick by German technology |
Project capacity |
28966 pieces a year |
Financial estimation of the project |
Total cost of the project, mln rubles |
200 mln. rbl. |
Investment capacity, mln rubles |
200 mln. rbl. |
Conditions of investor participation |
Direct investments |
Payback period |
5 years |
Land characteristics |
Location |
North-east part of Tbilisskaya village (300 m. to the north from cemetery and 1100m. to the east from military unit |
Land plot area (m2) |
40000 sq.m. |
Ground categories |
settlements land |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
from existing power station 110/35/10 kw |
1000 |
Gas supply |
from existing gas pipe with high pressure |
300 |
Water supply |
from existing water pipe d-160mm., free pressure in net 1,5 atm. |
1900 |
Sewerage system |
local |
|
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
Tbilisskaya village |
15 |
Center of federal subject |
Krasnodar city |
103 |
Highway (regional, federal significance) |
Temryuk-Krasnodar-Kropotkin |
2,3 |
Roads of local significance |
existing road with gravel surfacing |
0,5 |
Nearest railway station |
station of Grechishkino |
2,8 |
Nearest railway lines |
Krasnodar-Kropotkin |
0,45 |
Airport |
airport of Krasnodar |
93 |
Seaport |
port of Novorossiysk |
280 |