Project name |
Production on building materials release |
Location of the project |
Tbilisskiy district |
Industry classification |
Production of construction materials |
Basic information about the project |
Project essence |
Organization of production on building materials and tile release |
Project capacity |
30 thousand m? a year |
Financial estimation of the project |
Total cost of the project, mln rubles |
28,4 mln. rbl. |
Investment capacity, mln rubles |
28,4 mln. rbl. |
Conditions of investor participation |
Direct investments |
Payback period |
5,8 year |
Land characteristics |
Location |
West part of Tbilisskaya village, adjoins north border of mixed feed plant (industrial zone) |
Land plot area (m2) |
2000 sq. m. |
Ground categories |
Settlements land |
Characteristics of existing engineering infrastructure |
Infrastructure type | Capacity, diameter | Distance to the connection point (m) |
Power supply |
from existing power station 110/35/10 kw |
1000 |
Gas supply |
no necessary |
- |
Water supply |
from existing water pipe d-200mm., free pressure in net 1,5 atm. |
1850 |
Sewerage system |
local |
- |
Distance up to the large residential places and objects of transport infrastructure |
Remoteness from | Name | Distance (km) |
Municipality center |
Tbilisskaya village |
|
Center of federal subject |
Krasnodar city |
99 |
Highway (regional, federal significance) |
Temryuk-Krasnodar-Kropotkin |
0,25 |
Roads of local significance |
existing motorway with asphaltic concrete pavement |
0,8 |
Nearest railway station |
station of Grechishkino |
3,1 |
Nearest railway lines |
Krasnodar-Kropotkin |
0,9 |
Airport |
airport of Krasnodar |
90 |
Seaport |
port of Novorossiysk |
280 |