Construction of mix products shop

Project name Construction of mix products shop
Location of the project Goraychiy Kluych city
Industry classification Consumer sphere
Basic information about the project
Project essence Providing the first need necessities to the local inhabitants
Project capacity 45616 kg, 7814 pics
Financial estimation of the project
Total cost of the project, mln rubles 1,49 mln.rbl
Investment capacity, mln rubles 1,49 mln.rbl
Conditions of investor participation Direct investments
Payback period 4,6
Land characteristics
Location 353290, Goryachiy Klyuch city, village Octyabrskiy, Mira str., crossing Shkolnaya str.
Land plot area (m2) 200 sq.m
Ground categories Land of reserve
Characteristics of existing engineering infrastructure
Infrastructure typeCapacity, diameterDistance to the connection point (m)
Power supply 10 kVt 5
Gas supply Independent None
Water supply Construction of water reservoir None
Sewerage system Independent None
Distance up to the large residential places and objects of transport infrastructure
Remoteness fromNameDistance (km)
Municipality center Goryachiy Klyuch city 10
Center of federal subject Krasnodar city 60
Highway (regional, federal significance) FHW “Don” M-4 11
Roads of local significance Road “Goryachiy Klyuch – Khadijensk” 2
Nearest railway station Railway station of Goryachiy Klyuch 12.5
Nearest railway lines Railway station of Goryachiy Klyuch 12.5
Airport Krasnodar city 65
Seaport Novorossiysk city 160