Trade center placement

Basic information about ground area
The planned use of land Trade center placement
Location of the project Ust- Labinskiy district
Address of the location t. Ust-Labinsk, the North-Eastern part of the town, Volnaya Str. Railway crossing.
Cadastral number of quarter 23:35:0508016:43
Area of the declared (ì2) 1441
Category of the earths Area of settlements
Kind of permitted use Trade center placement
Actual use Not occupied
Availability of buildings, structures, constructions None
Authorizations, urban planning documentation General plan of the Ust-Labinsk settlement of the Ust-Labinsk District with reference to a part of Ust-Labinsk territory is developed by State Unitary Enterprise “Institute of the Krasnodar Region Territory Development”, authorized by the decision of the Ust-Labinsk settlement Council of the Ust-Labinsk District, dated 31.07.2007 ¹ 14, report of proceeding ¹ 2; “Rules of Land Tenure and Building of Tterritory of Ust-Labinsk District, Krasnodar Region with Reference to a Part of Territory of Settlement – t. Ust-Labinsk”, developed by the Kuban state agrarian university, authorized by the decision of the Ust-Labinsk settlement Council of the Ust-Labinsk District, dated 25.11.2008 ¹ 2, report of proceeding ¹ 35.
Information about the proprietor (legal owner) of the ground area
Proprietor Russian Federation
Legal owner Ust-Labinsk District Municipal Formation
Kind of rights -
Information about burden
Kind of burden, restrictions Communication cable, power transmission line 10kW, electric cable 0,4 kW, transforming station.
Area of burden 550 sq.ì.
The characteristic of existing engineering infrastructure
Kind of infrastructureCapacity, diameterDistance to a connection point (m)
Electrical supply 150 kilowatt Town’s net 301 block, 200 m
Gas supply Not required
Water supply 1,5 atmospheres, Tube O 100 mm Town’s net 301 block, 200 m
Water drain Local
Installation of telephones Not required
Cost of maintenance of the ground area an engineering infrastructure (Million rbl.) Water supply - 0,1; Sewerage - 0,2; Electro supply — 0,3
Distance till large settlements and objects of transport infrastructure
Remoteness fromThe nameDistance (km)
Center of municipal union t. Ust-Labinsk 3,5
Center of the subject of federation c. Krasnodar 65
Highways (regional, federal value) Temryuk-Krasnodar-Kropotkin 1,0
Highways of local value Volnaya Str. 0,02
The nearest railway station t. Ust-Labinsk 2,5
Nearest tracks t. Ust-Labinsk 0,1
Airport c. Krasnodar 50
Seaport c. Novorossiysk 230
The additional information about ground area
Special conditions The relief is mostly flat, subsoil waters is lower than 6 meters, subsidental subsoil, seismicity of the area - 8 points
Cost of rent/repayment of ground area (million rubles) 0,09