Apartment block placement

Basic information about ground area
The planned use of land Apartment block placement
Location of the project Ust- Labinskiy district
Address of the location t. Ust-Labinsk, block ¹ 305, area ¹ 1
Cadastral number of quarter 23:35:0550004:4
Area of the declared (ì2) 14 520
Category of the earths Area of settlements
Kind of permitted use Apartment block placement
Actual use Not occupied
Availability of buildings, structures, constructions None
Authorizations, urban planning documentation General plan of the Ust-Labinsk settlement of the Ust-Labinsk District with reference to a part of Ust-Labinsk territory is developed by State Unitary Enterprise “Institute of the Krasnodar Region Territory Development”, authorized by the decision of the Ust-Labinsk settlement Council of the Ust-Labinsk District, dated 31.07.2007 ¹ 14, report of proceeding ¹ 2; “Rules of Land Tenure and Building of Tterritory of Ust-Labinsk District, Krasnodar Region with Reference to a Part of Territory of Settlement – t. Ust-Labinsk”, developed by the Kuban state agrarian university, authorized by the decision of the Ust-Labinsk settlement Council of the Ust-Labinsk District, dated 25.11.2008 ¹ 2, report of proceeding ¹ 35.
Information about the proprietor (legal owner) of the ground area
Proprietor Russian Federation
Legal owner Ust-Labinsk District Municipal Formation
Kind of rights -
Information about burden
Kind of burden, restrictions High-pressure gas pipeline
Area of burden 1000 sq.ì.
The characteristic of existing engineering infrastructure
Kind of infrastructureCapacity, diameterDistance to a connection point (m)
Electrical supply 150 kWt Separated cell ÏÑ 35/10 kV «Ust-Labinsk-2», 3000 m
Gas supply Du 325, 16 atmospheres From the building high-pressure gas pipeline Du 325 town’s net Ust-Labinsk, 200 m
Water supply O 250 mm Connecting to the water pipeline Vigonnaya Str. 300 m
Water drain local
Installation of telephones local From Pionerskaya Str. 150 m
Cost of maintenance of the ground area an engineering infrastructure (Million rbl.) Water supply – 4,4; Sewerage - 3,0; Electro supply — 3,35; Heating supply – not required; Gas supply – 3,0; Telephone installation - 0,5
Distance till large settlements and objects of transport infrastructure
Remoteness fromThe nameDistance (km)
Center of municipal union t. Ust-Labinsk 3,7
Center of the subject of federation c. Krasnodar 65
Highways (regional, federal value) Temryuk-Krasnodar-Kropotkin 2
Highways of local value Volnaya Str. 0,9
The nearest railway station t. Ust-Labinsk 3,2
Nearest tracks t. Ust-Labinsk 1,2
Airport c. Krasnodar 50
Seaport c. Novorossiysk 230
The additional information about ground area
Special conditions The relief is mostly flat, subsoil waters is lower than 6 meters, subsidental subsoil, seismicity of the area - 8 points
Cost of rent/repayment of ground area (million rubles) 0,88
Notes -