Basic information about ground area |
The planned use of land |
The ground under construction of enterprise on processing of low-grade wood |
Location of the project |
Uspenskiy district |
Address of the location |
Krasnodar region, Uspensky district, bowery Veseliy, industrial zone |
Cadastral number of quarter |
23:34:08 02 001: |
Area of the declared (ì2) |
20 000 |
Category of the earths |
Lands of settlement. |
Kind of permitted use |
The zone of industrial construction |
Actual use |
Free territory |
Availability of buildings, structures, constructions |
- |
Authorizations, urban planning documentation |
The location of the project corresponds to town planning documentation – the general plan of bowery Vesely, Kubangiproselhozstroy, 1976. |
Information about the proprietor (legal owner) of the ground area |
Proprietor |
State property |
Legal owner |
Municipal formation. |
Kind of rights |
State property before delimitation. |
Information about burden |
Kind of burden, restrictions |
Absent |
Area of burden |
- |
The characteristic of existing engineering infrastructure |
Kind of infrastructure | Capacity, diameter | Distance to a connection point (m) |
Electrical supply |
0,4 kW |
5 |
Gas supply |
D=89mm |
85 |
Water supply |
D=100mm |
100 |
Water drain |
local |
- |
Installation of telephones |
- |
Connection according to specification of OJSC “UTK” |
Cost of maintenance of the ground area an engineering infrastructure (Million rbl.) |
0,295 |
Distance till large settlements and objects of transport infrastructure |
Remoteness from | The name | Distance (km) |
Center of municipal union |
v.Uspenskoe |
15 km |
Center of the subject of federation |
City Krasnodar |
250 km |
Highways (regional, federal value) |
Federal road “Caucasus” |
20 km |
Highways of local value |
«Uspenskoe-Armavir» |
17 km |
The nearest railway station |
rail road station “Konokovo” |
20 km |
Nearest tracks |
- |
20 km |
Airport |
Airport – city Mineralnie Vody |
150 km |
Seaport |
city Novorossisk |
400 km |
The additional information about ground area |
Special conditions |
The relief of the ground is calm, the soil mostly present by loam soft pliable; fine sand grayish-brown; pebble soil with sand filler. Underground water level is 1,0-1,4 m at 12.08.2002. Seismicity of ground: 7 points on the Richter scale. |
Cost of rent/repayment of ground area (million rubles) |
12,0/380,0 |
Notes |
- |