The ground under construction of enterprise on processing of low-grade wood

Basic information about ground area
The planned use of land The ground under construction of enterprise on processing of low-grade wood
Location of the project Uspenskiy district
Address of the location Krasnodar region, Uspensky district, bowery Veseliy, industrial zone
Cadastral number of quarter 23:34:08 02 001:
Area of the declared (ì2) 20 000
Category of the earths Lands of settlement.
Kind of permitted use The zone of industrial construction
Actual use Free territory
Availability of buildings, structures, constructions -
Authorizations, urban planning documentation The location of the project corresponds to town planning documentation – the general plan of bowery Vesely, Kubangiproselhozstroy, 1976.
Information about the proprietor (legal owner) of the ground area
Proprietor State property
Legal owner Municipal formation.
Kind of rights State property before delimitation.
Information about burden
Kind of burden, restrictions Absent
Area of burden -
The characteristic of existing engineering infrastructure
Kind of infrastructureCapacity, diameterDistance to a connection point (m)
Electrical supply 0,4 kW 5
Gas supply D=89mm 85
Water supply D=100mm 100
Water drain local -
Installation of telephones - Connection according to specification of OJSC “UTK”
Cost of maintenance of the ground area an engineering infrastructure (Million rbl.) 0,295
Distance till large settlements and objects of transport infrastructure
Remoteness fromThe nameDistance (km)
Center of municipal union v.Uspenskoe 15 km
Center of the subject of federation City Krasnodar 250 km
Highways (regional, federal value) Federal road “Caucasus” 20 km
Highways of local value «Uspenskoe-Armavir» 17 km
The nearest railway station rail road station “Konokovo” 20 km
Nearest tracks - 20 km
Airport Airport – city Mineralnie Vody 150 km
Seaport city Novorossisk 400 km
The additional information about ground area
Special conditions The relief of the ground is calm, the soil mostly present by loam soft pliable; fine sand grayish-brown; pebble soil with sand filler. Underground water level is 1,0-1,4 m at 12.08.2002. Seismicity of ground: 7 points on the Richter scale.
Cost of rent/repayment of ground area (million rubles) 12,0/380,0
Notes -