Basic information about ground area |
The planned use of land |
Building of a trading-household complex |
Location of the project |
Timashevskiy district |
Address of the location |
Krasnodar territory, Timashevsk, Zarya district, 27 Selskaya street |
Cadastral number of quarter |
23: 31: 03 15 002 |
Area of the declared (́2) |
4481 (m2) |
Category of the earths |
The earths of settlement |
Kind of permitted use |
Zone of individual housing construction, territory for placing of objects of public appointment |
Actual use |
Temporarily are not used |
Availability of buildings, structures, constructions |
Objects of the real estate are absent |
Authorizations, urban planning documentation |
According to the general plan of building of the city of Timashevska developed by the State unitary enterprise «Institute of territorial development of Krasnodar territory» 2005. |
Information about the proprietor (legal owner) of the ground area |
Proprietor |
State ownership |
Legal owner |
Municipal union administration Timashevsky area |
Kind of rights |
The unlocated state ownership which is in conducting Timashevsky City settlement |
Information about burden |
Kind of burden, restrictions |
Absent |
Area of burden |
- |
The characteristic of existing engineering infrastructure |
Kind of infrastructure | Capacity, diameter | Distance to a connection point (m) |
Electrical supply |
25 thousand in kw-h |
10́. From the existing Electrolines |
Gas supply |
12 cubic m a year |
20 m from an existing gas pipeline of average pressure |
Water supply |
15 cubic m./days |
350 m - from the Existing waterpipe, on street Collective-farm |
Water drain |
15 cubic m./days |
Projected treatment facilities |
Installation of telephones |
The user\'s payment will roughly make 5 thousand rbl. |
300 m. from Existing electroline |
Cost of maintenance of the ground area an engineering infrastructure (Million rbl.) |
Water supply: 1,1 million rbl. The water drain waste âîä:. 0,12 million rbl. Electrosupply: 0,25 million rbl. Heat supply: 0,5 million rbl. Gas supply: 0.4 million rbl. Installation of telephones: 0,06 million rbl. Total: 2.43 million rbl. |
Distance till large settlements and objects of transport infrastructure |
Remoteness from | The name | Distance (km) |
Center of municipal union |
The city of Timashevsk |
7 km |
Center of the subject of federation |
The city of Krasnodar |
73 km |
Highways (regional, federal value) |
Krasnodar - Yeysk |
4 km |
Highways of local value |
Street Collective-farm in Timashevsky |
10 km |
The nearest railway station |
Station Timashevsky |
9 km |
Nearest tracks |
City Timashevsk |
9 km |
Airport |
The city of Krasnodar |
96 km |
Seaport |
Novorossiysk |
164 km |
The additional information about ground area |
Special conditions |
Seismicity of 7 points, level of subsoil waters of 3-5 m |
Cost of rent/repayment of ground area (million rubles) |
Cost of rent of the ground area makes 273228,97 rbl. a year Cost of the repayment of the ground area will make 1429544,3 rbl. |