Basic information about ground area |
The planned use of land |
Shop "Flowers" building |
Location of the project |
Timashevskiy district |
Address of the location |
Krasnodar territory, Timashevsky area, the item Novokorsunsky, street Guerrilla, 83 A |
Cadastral number of quarter |
23: 31:05 02 003 |
Area of the declared (ì2) |
204 (m2) |
Category of the earths |
The earths of settlement |
Kind of permitted use |
Socially-business zone |
Actual use |
It is not used |
Availability of buildings, structures, constructions |
Objects of the real estate are absent |
Authorizations, urban planning documentation |
According to the general plan Perspective development of the item Novokorsunsky, The developed institute «Edge collective farm the project» in 1984 |
Information about the proprietor (legal owner) of the ground area |
Proprietor |
State ownership |
Legal owner |
Municipal union administration Timashevsky area |
Kind of rights |
Unlocated state ownership being in management administration of Novokorsunsky rural settlement |
Information about burden |
Kind of burden, restrictions |
- |
Area of burden |
- |
The characteristic of existing engineering infrastructure |
Kind of infrastructure | Capacity, diameter | Distance to a connection point (m) |
Electrical supply |
300 kw |
20 m. from the existing Electrolines |
Gas supply |
Steel, Diameter of 108 mm |
25 m. from an existing gas pipeline Low pressure |
Water supply |
Astbesto-cement, Diameter of 100 mm |
12 m from an existing waterpipe |
Water drain |
Astbesto-cement, Diameter of 250 mm |
30 m. in the existing Drainage system |
Installation of telephones |
15 pair |
5 m. from an existing line |
Cost of maintenance of the ground area an engineering infrastructure (Million rbl.) |
Water supply: 0,01 million rbl. The water drain waste âîä:. 0,03ìëí.ðóá Electrosupply: 0, 021 million rbl. Heat supply: 0,06 million rbl. Gas supply: 0,025 million rbl. Installation of telephones: 0,01 million rbl. Total: 0,147 million rbl. |
Distance till large settlements and objects of transport infrastructure |
Remoteness from | The name | Distance (km) |
Center of municipal union |
The city of Timashevsk |
20 |
Center of the subject of federation |
The city of Krasnodar |
90 |
Highways (regional, federal value) |
Timashevsk-Korenovsk |
4,0 |
Highways of local value |
The item Novokorsunsky,bStreet Red |
0,045 |
The nearest railway station |
Station Timashevsky |
25 |
Nearest tracks |
Station Timashevsky |
25 |
Airport |
The city of Krasnodar |
80 |
Seaport |
Novorossiysk, Yeysk, Temryuk |
200, 230, 130 |
The additional information about ground area |
Special conditions |
Seismicity of 7 points, level of subsoil waters of 1,7-6 m. |
Cost of rent/repayment of ground area (million rubles) |
Cost of lease of the ground area Makes 0,005049 million rbl. a year Cost of the repayment of the ground area Will make 0,01768925 million rbl |
Notes |
¹16 |